Annursnac Hill Rd. Guardrail Project

Project:

2020 Annursnac Hill Road Guardrail Replacement Project

Town Contacts:

Joseph Cormier, Associate Engineer, Concord Public Works (CPW)– Engineering Division, 978-318-3210, jcormier@concordma.gov

General Contractor:

Steelco Chain Link Fence Erecting Co., Inc.

Project Schedule:

Construction has been completed as of July 2, 2021. 

Project Overview:

The goal of this project was to replace the out dated and deteriorating roadside guardrail along Annursnac Hill Road. Engineering Division has planned and designed phase two of the guardrail replacement for the Annursnac Hill Road neighborhood.  Phase two consisted of the removal and replacement of 1,242 feet of guardrail with timber post Cor-Ten weathering steel guardrail. The Section of Guardrail replaced is located between 309 and 451 Annursnac Hill Road. Steelco Chain Link Fence Erecting Co. was awarded the bid for this project and carried out the construction.

Construction Status:

Completed